PROJECTTASKPLANNEDENDDATE function

Created by Harry Lewis, Modified on Thu, 05 Oct 2023 at 05:50 PM by Gabriel Michaud

Applies to

  • Velixo NX
  • Velixo Classic
  • Acumatica, MYOB Advanced, Cegid

 

Description

The PROJECTTASKPLANNEDENDDATE function returns the planned end date of a project task.


Syntax

PROJECTTASKPLANNEDENDDATE(Connection, Project, ProjectTask)

Parameters

The PROJECTTASKPLANNEDENDDATE function uses the following parameters:

 

Parameter

Required/Optional

Description

Connection

Required

The name of the connection as configured in the Connection Manager

Project 

Required

The ID of the Project to include

ProjectTask 

Required

The ID of the Task to include

Example

=PROJECTTASKPLANNEDENDDATE("Demo", "INTERNAL14", "03SOFTWARE")

 

Description

Returns the planned end date of the 03SOFTWARE task in the INTERNAL14 project.

 

Result

42004

 

Note that the results are returned as a serial number - to match Excel's default treatment for dates. The cell can be formatted to any date format desired.


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article